What is Float?

Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available:

  • Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities.
  • Total Float: It is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating schedule constraint.

Float is calculated by using the critical path method technique.

Share

About Mark Smith

I am passionate about reading. I love to read anything, whether it is an article, a blog post, an advertisement, a piece of old newspaper, anything. I am a full-time trainer and love to interact with people. I enjoy what I do and love the world. I request all the readers go green. Plant a tree to make a day memorable. Plant a tree on your Birthdays, Anniversaries, your child's birthdays, etc. Spread these words, lots of trees is to be planted to make our environment healthy.
This entry was posted in PgMP, PMP and tagged . Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>