Control Schedule
The Control Schedule process is one of the ten processes grouped under the Monitoring and Controlling Process group. The Control Schedule process is the process of monitoring the status of the project to update project progress. It is also the process of managing changes to the schedule baseline.
Inputs
There are four inputs in the Control Schedule process:
- Project management plan
- Project schedule
- Work performance information
- Organizational process assets
Outputs
There are the following five outputs in the Control Schedule process:
- Work performance measurements
- Organizational process assets updates
- Change requests
- Project management plan updates
- Project document updates