Daily Archives: March 14, 2010

What is project schedule network diagram?

Project Schedule Network Diagrams The project schedule network diagrams are outputs of the Sequence Activities process. These diagrams are schematic displays of the project’s schedule activities. These diagrams also displays the logical relationships amount the scheduled activities. These diagrams can … Continue reading

Share
Posted in CAPM, PMP | Tagged , , | 1 Comment

What is RFP?

Request for proposal (RFP) is a type of procurement document. The RFP is used to request proposals from prospective sellers of products or services. It is an invitation for suppliers, often through a bidding process, to submit a proposal on … Continue reading

Share
Posted in CAPM, PgMP, PMP | Tagged , , , | Leave a comment